Phu Binh: Over 20 billion VND invested in renovating and upgrading the power grid system
In order to meet the electricity needs of the people, since the beginning of the year, Phu Binh Power Company has invested 20.3 billion VND (from the budget allocated by the Northern Power Corporation) to build new, upgrade and renovate the power grid system in the area.
From the above budget, the unit has built new, upgraded 7.3km of medium voltage grid to prevent overload and upgraded 20 transformer stations with a total capacity of 6,180 kVA; built new 33.3km of low voltage lines; renovated 32.5km of low voltage lines; major repairs and regular repairs of 26 items.
Currently, Phu Binh Power Company is managing 351.27km of medium voltage lines, 759.24km of 0.4kV lines, 296 transformer stations. Thanks to regular renovation and upgrading, the power grid system in the district is increasingly improved and developed, contributing to improving voltage quality and reducing power loss. The rate of households using electricity regularly and safely is 100%.